Another busy week saw us with 2 days of crane lift to block 1. On Monday we placed the ground floor wall panels in position, Wednesday we lifted the floor cassettes in position. Then we braced the gable and party wall roof panels on the 1st floor ready for the truss delivery next week , which we set out on the 1st floor. Blocks 2 and 3 also progressed well fixing the 2 layers of plasterboard to the perimeter walls and ceiling. These then get sealed at the floor and ceiling to form an air tight envelope. With the weather on our side the masonry to block 3 is up to the 2nd lift.