Friday, 26 July 2013

This week the groundworkers returned to site and started to connect the rainwater pipe gullies. Internally in block 1 we are plastering the last plot and are continuing fitting kitchens, 2nd fix M&E and started tiling the kitchens and toilets. In blocks 2 and 3 we are boxing in the MVHR units and the toilet pipe boxing. Next week we can snag the walls ready for final decoration.
 


 

Tuesday, 23 July 2013

On Block 1 the masonry is complete including the dentil course on the Combs road elevation. Also we completed the render, therefore enabling us to commence stripping the scaffold.
Internally we have started fitting the kitchens and 2nd fix M&E. In Block 3 we have hung the doors and fitted the ironmongery and started hanging the doors in Block 2.
 

 

Friday, 5 July 2013

5th July 2013

On Block 1 we have almost complete the masonry with just the dentil course under the soffit. This will enable us the start the rendering next week. Internally is much the same carrying on 1st fix M&E following on with the plastering. The kitchens for 4 plots are due next week. Blocks 2 and 3 kitchens are complete. We are carrying on 2nd fix joinery in Block 2. Next week the doors are been deliverered so we can start hanging and fixing the ironmongery in Block 3

Tuesday, 2 July 2013

Busy week so far!

On Block 1 the masonry is almost complete with just the gable and returns to plots 1 and 2 to finish off. Internally we have commenced plastering following on from the ongoing 1st fix M&E. On Blocks 2 and 3 the scaffold has been stripped apart from the entrance platforms. In Block 2 work on the kitchens and 2nd fix joinery have started. In Block 3 the kitchens, architraves and skirting are complete as well as the fitting the electrical sockets and switches. We will be fitting the toilets so we can complete the boxing in of the pipe work.