This week on Block 1 we got the scaffold ready for timber frame erection next Monday. The roofers continued tiling from Block 3 to Block 2. With the blocks now water tight we installed the insulation to the party wall and ceilings, enabling the dryliners to plasterboard the ceilings and walls. The bricklayers have also started on Block 3. We are really picking up pace with more work been available for the follow on trades.
 



 
 