This week on block 1 we continued externally with the masonry. Internally we continued with the 1st fix m&e. Also the joiners fit the kitchen and cupboard pattrasses which then enabled us to close the first plot and commence plastering. On blocks 2 and 3 we have started stripping the scaffold. Internally we have completed the skirting and architraves and started tiling the bathrooms and kitchens.
Friday, 21 June 2013
Friday, 14 June 2013
Another good week saw us progress with the masonry to block 1 and start 1st fix mechanical also set out and board one side of the walls. In block 2 we have completed the plastering, once this as dried we can mist coat and 2nd fix the M&E. In block 3 we are fitting the kitchens and 2nd fix joinery (skirtings and architraves). The tiling is to start next week.
Friday, 7 June 2013
The roof on Block 1 is complete and the masonry to Block 2 is also complete. This will enable the render to start next week on Blocks 2 and 3. We are progressing with the masonry on Block 1. Internally we are continuing 2nd side boarding in Block 2. In Block 3 we are in the last plot plastering and started 2nd fix joinery and M&E.
Subscribe to:
Posts (Atom)