This week we lifted the  the roof trusses off the 1st floor, erected the perimeter walls and repositioned the roof trusses back on the walls. This as allowed us to commence felt and battening the roof. Externally on Blocks 2 and 3  we are carrying on with the masonry and the internals are progressing with the 1st fix mechanical. This week we have commenced the 1st fix electrical and plywood pattresses to the bathrooms, kitchens and cupboards.