Wednesday, 29 May 2013

On Block 1 we completed the timber frame erection with enabled us the lath and felt the roof and start tiling. This also as enabled us to commence the plasterboard the perimeter walls.
Block 3 the masonry is complete and on Block 2 it is up to the 2nd lift. Internally we are continuing with the 1st fix m&e and closing the walls ready for plastering next week after the Bank Holiday.
 


 