Friday, 10 May 2013

After the Bank Holiday we were straight back into it with a crane lifting the trusses onto the 1st floor to enable us to set out the trusses. The masonry is progressing well on block 3 past the 2nd lift . We also started the masonry on block 2 up to dpc. Internally we are carrying on with fixing the perimeter service battens and setting out the internal walls which as enabled the 1st fix mechanical to start. 1st fix electrical will follow next week.
 


 