Friday, 26 July 2013

This week the groundworkers returned to site and started to connect the rainwater pipe gullies. Internally in block 1 we are plastering the last plot and are continuing fitting kitchens, 2nd fix M&E and started tiling the kitchens and toilets. In blocks 2 and 3 we are boxing in the MVHR units and the toilet pipe boxing. Next week we can snag the walls ready for final decoration.
 


 