Tuesday, 2 July 2013

Busy week so far!

On Block 1 the masonry is almost complete with just the gable and returns to plots 1 and 2 to finish off. Internally we have commenced plastering following on from the ongoing 1st fix M&E. On Blocks 2 and 3 the scaffold has been stripped apart from the entrance platforms. In Block 2 work on the kitchens and 2nd fix joinery have started. In Block 3 the kitchens, architraves and skirting are complete as well as the fitting the electrical sockets and switches. We will be fitting the toilets so we can complete the boxing in of the pipe work.