Friday, 5 July 2013

5th July 2013

On Block 1 we have almost complete the masonry with just the dentil course under the soffit. This will enable us the start the rendering next week. Internally is much the same carrying on 1st fix M&E following on with the plastering. The kitchens for 4 plots are due next week. Blocks 2 and 3 kitchens are complete. We are carrying on 2nd fix joinery in Block 2. Next week the doors are been deliverered so we can start hanging and fixing the ironmongery in Block 3